January 29, 2021
Subject to Change
Below please find our development schedule. Please note the schedule is subject to change.
| SOFTDEMO/ABATEMENT |
7/15/2020 – 11/15/2020 |
| DEMO |
11/15/2020 – 3/1/2021 |
| SHEETING + SHORING |
2/1/2021 |
| EXCAVATION |
3/15/2021 – 9/15/2021 |
| CONCRETE G3-10TH |
10/1/2021 – 12/1/2022 |
| CURTAIN WALL ONSITE |
11/1/2022 – 9/10/2023 |
| CONCRETE 11TH – 18TH |
12/1/2022 – 2/10/2023 |
| CONCRETE 19TH – HOTEL ROOF (35TH) |
2/13/2023 – 7/28/2023 |
| EXTERIOR FRAMING |
4/1/2023 – 10/1/2023 |
| EXTERIOR MASONRY |
5/1/2023 – 12/1/2023 |
| WINDOWS RESIDENTIAL |
7/1/2023 – 1/15/2024 |
| RESIDENTIAL ROOF |
1/2/2024 – 4/1/2024 |
| CORE + SHELL |
4/1/2024 |
| OCCUPANCY/MOVE-INS |
5/1/2024 |